Some systems are experiencing issues

Past Incidents

2nd December 2020

No incidents reported

1st December 2020

DDos Attack

We are currently experiencing a DDoS attack.

More information on this can be found here - https://en.wikipedia.org/wiki/Denial-of-service_attack

We hope to have normal service resumed soon.

  • We are now marking this incident as resolved.

  • At its peak we were taking in 15Gb/s of DDOS traffic destined for a customer in our network. We have located this customer and we are now filtering traffic, all services are now stable.

  • 30th November 2020

    No incidents reported

    29th November 2020

    Fixed Wireless Access

    We're investigating an issue on the Fixed Wireless Access network affecting customers in the East Wight area.

  • Following several hours running on a backup generator, our mast in Merstone has not returned to running on mains. We recently upgraded the backup battery system in this mast, it has now been identified that there is a minor design fault - resulting in an outage it in the network this evening. We are sorry for the disruption to service – the design fault will be rectified in the next day or so.

    For those of you slightly techy or just interested read below: -

    The equipment running in our mast sites is low voltage DC – the site in question is a 24 volts (nominal) DC. Essentially what all our sites have is a DC rectifier stepping 230VAC down to a stable 28.5volts DC which is fed into a DC UPS. The DC UPS floats the backup batteries and supplies the DC Current to the load (our kit, the kit that supplies your service).

    The MAIN Fuses on this site are 10AMPS which at 28.5v were doing the job quite nicely.

    280watt load @ 28.5volts = 9.8 Amps.

    This evening our site suffered a mains failure (this is pretty normal this time of year) the load was automatically transferred over to the battery bank – our proactive monitoring alerted us, but with a 20 hour run time on battery this is classed as an ‘information’ alert. We need to be aware that the site is running on battery, but everything is in hand the service is not at risk – so you can imagine our surprise 45 minutes later when the mast shut down. Now for the theory.

    As batteries discharge the voltage decreases, and when the voltage decreases the amperage increases. This is known as Ohm’s law, more on that here.

    The open circuit voltage of our batteries at 100% Charge is 25.48 Volts. 280watt load @ 25.48volts = 11 Amps.

    The open circuit voltage of our batteries at 80% Charge is 24.2 Volts. 280watt load @ 24.2volts = 11.7 Amps.

    At which point our 10AMP main fuses just could not take it anymore!!

    The power system on this mast site is ‘the standard’ across our wireless network. This site however has become a bit of an aggregation point for several masts and therefore has several high capacity radio links on which do draw quite a bit power compared to other mast in the network.

    So the root cause of this incident is that the load calculations did not take into consideration the increased amperage during discharge conditions on the battery bank.

  • 28th November 2020

    No incidents reported

    27th November 2020

    No incidents reported

    26th November 2020

    No incidents reported

    25th November 2020

    Fixed Wireless Access - Isle of Wight Planned Maintetence 25/11/2020 00:01 to 06:00

    Planned maintenence on the Isle of Wight fixed wireless access network is beginning. We'll update this status when works have been completed.

  • This evenings maintenance has been completed with success, all alarms on our proactive monitoring are clear and the network has returned to a normal operational state.

    If you are still experiencing a loss of service, please power down your equipment at the wall socket for a few moments before powering back on. Please do not be tempted to press any reset buttons (it will only make it worse).

    If you are still experiencing loss of service after powering down your equipment for a few minutes, please get in touch with us on 01983770000.